Apply template to a blank project in project workspace

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • When you create a new project in the project workspace, you can apply a template.

    시작하기 전에

    Role required: it_project_manager

    이 태스크 정보

    A project created from the off-schedule project template honors the off-schedule tasks and adjusts the dates according to the given start date.

    When applying a template to a project, the project state is set to the default state. Activate the default project state (pm_project.state = -5), and use it as the default value as it is Out Of The Box. You can update the label for the State field to meet your requirements if Pending doesn't fit well.

    프로시저

    1. Navigate to All > Project > Projects > Project Workspace.
    2. In the project workspace header, select New.
    3. Enter the project name, select the start date, and select a template in Create Project dialog box.
    4. Select OK.