Starting a project
Initiate a project by changing the project state to Work in Progress. Define important aspects of your Agile, Waterfall, or Hybrid project such as the duration, estimated cost, and net value to your organization to efficiently track the project's progress.
시작하기 전에
Role required: it_project_manager
이 태스크 정보
When you change the State field on the Project form to Work in Progress, the Actual start date of the project changes to the planned start date.
- The read-only Actual start date field of the project is populated with the planned date.
- If a task or set of tasks are scheduled to start immediately upon project start (meaning that their time constraints are set to Start ASAP and they have no other start dependencies), the actual start dates of those tasks also get populated with the planned date.
- The planned start dates of all other tasks adjust accordingly based on the time you started the project. Their new planned start dates depend on several factors, including dependent relationships with other tasks and the
duration for each task.주:Once a project is in the Work in Progress state, it does not mean that the state of every task will start updating automatically based on planned start date. Other than the project tasks that you schedule to start ASAP when the project starts, project tasks are not started automatically. Continue to manage the project and change the state of each task to Work in Progress.
You can also use the multi-currency feature to create a project in a local currency different from your functional currency. You must enable the PPM Standard Multicurrency plugin (com.snc.ppm_multicurrency) and switch to the Project Currency view for the additional fields in the Financials tab of the Project form. For more information, see Multi-currency in project financials.