Modify a project task dependency

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.

    시작하기 전에

    Role required: it_project_manager

    이 태스크 정보

    Project task dependencies are saved on the Planned Task Relationship [planned_task_rel_planned_task] table. You can access dependencies from the planning console.

    프로시저

    1. Double-click a dependency on the Gantt chart of the planning console.
    2. On the form, fill in the details.

      For more information, see Planned Task Relationship form.

      그림 1. Planned Task Relationship form
      Planned Task Relationship form
    3. Select Update.
      You can view dependencies in the Project Task related list on a Project or Project Task form and from the Project Tasks list on the workbench. These columns show the dependencies: