Planned Task Relationship form

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Learn about the fields of planned task relationship form.

    표 1. Planned Task Relationship form fields
    Field Description
    Predecessor The predecessor, or determiner, in the relationship. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks.
    Successor The successor in the relationship. The successor depends on the predecessor. You can select a new task. However, it is a good practice to delete the relationship and create a new relationship between the correct tasks.
    Type The type of relationship, which is always Predecessor of::Successor of. Do not change this value.
    Sub Type The type of dependency.
    Lag The lag time between the tasks. The Enter the days, hours, minutes, and seconds for the lag. Lag time can be positive or negative.