Recalculate costs of resource assignments of a demand

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 2분
  • Recalculate the costs of all active resource assignments of a demand whenever the hourly rates change in the associated rate model so that the plan costs are up to date.

    시작하기 전에

    Confirm the following setup:
    • The demand must be active.
    • The demand must have an active rate model assigned.
    Role required: demand_manager

    이 태스크 정보

    This option recalculates the costs of all resource assignments of the demand at once. You can also open a resource assignment from the Resource assignments related list to recalculate the resource costs of an individual resource assignment.

    프로시저

    1. Navigate to All > Demand > Demands > All.
    2. Open a demand.
    3. On the Demand form, right-click on the header bar and select the Recalculate Resource Costs.
    4. In the Recalculate Resource Cost form, fill in the fields.
      For a description of the field names, see Recalculate resource costs form.
    5. Select OK.

    결과

    • Recalculates the selected resource costs of all the applicable resource assignments in the demand based on the latest hourly rates. The hourly rates are derived from the rate model associated with the demand.
    • Updates the recalculated resource costs on the respective cost fields on the resource assignment form and the Resource assignments related list.
    • Reflects the revised values in the respective cost fields of the demand.