Add, edit, or delete demand cost plans

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 5분
  • Create a cost plan for a required duration to track your planned and actual expenses. Edit cost plans to adjust your planned expenses and delete any descoped forecasts.

    시작하기 전에

    Role required: it_demand_manager

    이 태스크 정보

    The application automatically creates cost plan breakdown records when you save the cost plan. The cost plan breakdowns are records that specify the estimated and actual costs and the budget at a granular level for specific fiscal periods, such as FY16: M04 and FY16: M05. The demand cost plans are added to the parent program and portfolio.

    If you want to use multiple currencies, create a cost plan for another currency.

    If you’re creating a cost plan for a demand with the PPM Standard Multicurrency (com.snc.ppm_multicurrency) plugin activated and Demand Currency view enabled, the fields in the Financials section differ from the Default view. For more information about the fields that are available only in the Demand Currency view, see Multicurrency in Next Experience for Demand Management reference.

    주:
    For projects, the cost plan breakdowns specify the estimated cost and actual cost at a granular level for a fiscal period of the demand cost plan. These breakdowns are recalculated in the project currency. Similarly, the estimated breakdown amounts of the planned benefit and actual benefit of the demand benefit plans are recalculated in the project currency. The project currency amounts are then rolled up to the cost plan, benefit plan, and the project records.

    프로시저

    1. Open a demand from the home page of Next Experience for Demand Management.
      For more information, see Access demands.
    2. Select Details from the L-2 (level 2) navigation menu.
    3. Select Cost Plans.
      주:
      If the Cost Plans tab isn’t visible, select More and then select Cost Plans.
      ChoiceDescription
      To create a cost plan
      1. Select New.
      2. On the Create New Cost Plan form, fill the fields.

        For a description of the field names, see Create cost plan form.

      3. Select Save.
      To edit a cost plan Select the name of the cost plan, edit the required details and select Save.
      To view and manage cost plan breakdowns
      1. Select the name of the cost plan.
      2. Select Cost Plan Breakdowns.
      3. Select a fiscal period.
        • To edit a fiscal period record, edit the name and select Save.
        • To delete a fiscal record, select Delete from the More Actions option in the fiscal period record form.
      To create cost plan breakdowns
      1. Select the name of the cost plan.
      2. Select Cost Plan Breakdowns.
      3. Select New. For more information about the fields, see Create cost plan breakdown form.
      4. Select Save.
      To delete a cost plan Delete a cost plan in one of the following ways:
      • Select a record from the Cost Plans tab and select Delete.
      • Select Delete from the More Actions option in the cost plan form.
      주:
      Deleted cost plans and the associated expense lines can’t be recovered.
      팁:
      Create financial baselines immediately after capturing the initial planned costs to have a snapshot of your planned costs. Use this baseline to compare it against the baselines from later dates, as the work progresses, to identify the variance between initial planned costs and actual expenses.

      This step helps you to plan for the future expenses and re-forecast the planned costs.

      Alternatively, you can create, edit, or delete cost plans and cost plan breakdowns using the Estimate financial cost playbook activity. For more information, see Use Playbooks.