Realign resource assignments with demand

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Planning and execution of your roadmap involves change in priority or timelines of your work. In such cases, you can adjust the resource assignment dates to match with the latest dates of your demands.

    시작하기 전에

    Migrate resource plans to resource assignments

    Role required: it_demand_manager

    프로시저

    1. Navigate to All > Demand > Demands > All.
    2. Open the required demand.
    3. Change the Approved start date and Planned start date to meet your organizational priorities.
    4. Select Save.
    5. Select the Realign assignments to demand related link.

    결과

    In the Resource assignments related list, you can see the Start date of the resource assignments aligned with the demand start dates.