Realign resource assignments with demand
Planning and execution of your roadmap involves change in priority or timelines of your work. In such cases, you can adjust the resource assignment dates to match with the latest dates of your demands.
시작하기 전에
Migrate resource plans to resource assignments
Role required: it_demand_manager
프로시저
- Navigate to .
- Open the required demand.
- Change the Approved start date and Planned start date to meet your organizational priorities.
- Select Save.
- Select the Realign assignments to demand related link.
결과
In the Resource assignments related list, you can see the Start date of the resource assignments aligned with the demand start dates.