Remove a dependency

  • 릴리스 버전: Australia
  • 업데이트 날짜 2026년 03월 12일
  • 소요 시간: 1분
  • Use the planning console to remove a dependency that is no longer necessary.

    시작하기 전에

    Role required: it_project_manager

    이 태스크 정보

    Removing the dependency also deletes the dependency record in the Planned Task Relationship table.

    프로시저

    1. Open the project in the planning console.
    2. Do either of the following.
      옵션설명
      On the Gantt chart
      • Right-click the relationship and then select Delete Link.
      • Double-click the relationship and then select Delete on the Planned Task Relationship form that appears.
      On the WBS list
      • Delete the value in the Predecessor column.
      • Select the value in the Predecessor column and then select Delete on the Planned Task Relationship form that appears.