Remove a dependency
Use the planning console to remove a dependency that is no longer necessary.
시작하기 전에
Role required: it_project_manager
이 태스크 정보
Removing the dependency also deletes the dependency record in the Planned Task Relationship table.
프로시저
- Open the project in the planning console.
-
Do either of the following.
옵션 설명 On the Gantt chart - Right-click the relationship and then select Delete Link.
- Double-click the relationship and then select Delete on the Planned Task Relationship form that appears.
On the WBS list - Delete the value in the Predecessor column.
- Select the value in the Predecessor column and then select Delete on the Planned Task Relationship form that appears.