Change task groups

VenkataSreC
Tera Contributor

When change request is created two change tasks created in implementation state when we open those tasks there is an assignment group field is there when I click on assignment group I want only the implementation groups visible I don’t want any other groups will appear how to do that please guide steps

8 REPLIES 8

Chaitanya ILCR
Mega Patron

Hi @VenkataSreC ,

 

you can create a dictionary override for change_task table on assignment group field and add a reference qualifier to only show the implementation groups

 

is there any criteria to know that a group is a implementation group? like group type or something if yes add  the reference qualifier on the dictioarny override 

 

Please mark my answer as helpful/correct if it resolves your query.

Regards,
Chaitanya

In reference qualifier what I want to keep like script or conditions

Ankur Bawiskar
Tera Patron
Tera Patron

@VenkataSreC 

how are you identifying implementation groups?

Is it based on group type?

Remember assignment group field is on task table so you will have to create dictionary override for change_task and add your reference qualifier there

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 9x ServiceNow MVP  ||  ✨ ServiceNow Community Leader

@VenkataSreC 

Hope you are doing good.

Did my reply answer your question?

If my response helped please mark it correct and close the thread so that it benefits future readers.

Regards,
Ankur
✨ Certified Technical Architect  ||  ✨ 9x ServiceNow MVP  ||  ✨ ServiceNow Community Leader