Hi,

 

Can someone please help me on how to create a report to track the duration a change request is with approvers?

 

Thanks for your help in advance!!

2 REPLIES 2

Rohit  Singh
Mega Sage

Hi @vivianlowra 

 

There is a field on the task table called "approval_set". This should be populated with a date/time when a record has been approved and  corresponding to your change_request Record .

You can report on the span from the field opened.

 

You can also create a metric to calculate the duration for easier reporting.

RohitSingh_0-1744039292608.png

 

 

If my response helped, please hit the Thumb Icon and accept the solution so that it benefits future readers.

 

Regards,
Rohit

Hi @vivianlowra ,

 

Did you check my response?

 

If my response helped, please hit the Thumb Icon and accept the solution so that it benefits future readers.

 

Regards,
Rohit