04-07-2025 07:09 AM
Hi,
Can someone please help me on how to create a report to track the duration a change request is with approvers?
Thanks for your help in advance!!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-07-2025 08:21 AM
Hi @vivianlowra
There is a field on the task table called "approval_set". This should be populated with a date/time when a record has been approved and corresponding to your change_request Record .
You can report on the span from the field opened.
You can also create a metric to calculate the duration for easier reporting.
If my response helped, please hit the Thumb Icon and accept the solution so that it benefits future readers.
Regards,
Rohit
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-07-2025 09:36 PM
Hi @vivianlowra ,
Did you check my response?
If my response helped, please hit the Thumb Icon and accept the solution so that it benefits future readers.