Change Risk Assessment and fields on the form

Sam Ogden
Tera Guru

Hi All,

We are in the middle of revamping our change process.  As part of this I've installed the change Management - Risk Assessment v2 plugin.  My change manager has created a risk assessment, however a couple of the risk assessment questions are either also on the form or can be derived from information on the form.  I was wondering if it is possible to have the calculation run based off the answers on the risk assessment and also some fields on the form?

If this is not possible, can I default answers on the risk assessment based off values in fields on the form, or is it possible to fill in values in fields on the form based off answers from the risk assessment?

Thanks

Sam

7 REPLIES 7

Hello Sam,

Did you got the solution or design of how to implement ? We are also considering the similar requirement.

Hi Bharath,

I've since changed companies, but from memory I think we ended up having different risk assessments i.e. one that was required when the environment was 'production' with certain scored, and a different risk assessment for when the environment was 'non-production' with different scores.

Hope this helps 

Thanks

Sam

Hey thanks for the reply Sam.

QQ if you remember the process, How did you display different Risk assessments based on change form field (prod vs non prod) , condition on UI actions or can we apply those conditions on Risk assessments page ?