I have a flow that I have 6 tasks that are worked in parallel.  There is a select question on each task that has 3 options, Yes, yes with comments and no with comments.

 

the field names are

approved_by_ops

approved_by_it_infrastructure

approved_by_asset_management

approved_risk_mgmt

approved_by_grc

approved_by_is_security

 

If any one of the above questions answer no with comments.  I need the remaining open tasks to automatically close skipped.

 

I cant come up with a good solution to make this happen.  Any thoughts would be greatly appreciated.

 
 
 

 

 

 

6 REPLIES 6

Sounds good

Thank you so much for your solution.  I appreciate you taking the time to write it all out.  I will give your solution a try.