Hi,

 

How the Issue Triage ticket related to the Risk event in IRM,

when we raise Issue from protal, issue triage ticket will create then how the flow goes to risk event?

2 REPLIES 2

Dr Atul G- LNG
Tera Patron
Tera Patron

Hi @Arun_Manoj 

Sharing this based on my recent experience—I've just completed the GRC batch, and I'm passing along what I’ve learned.

Triage mainly depends on triage rules and assignment rules. Unfortunately, it didn’t work for me when I raised the issue from ESC, but it did work when I raised it from the Service Portal.

I’d recommend exploring these areas further to identify what might be causing the difference.

 

You can check the GRC course or now create docs as well.

 

DrAtulGLNG_0-1752234082810.png

https://www.servicenow.com/docs/bundle/yokohama-governance-risk-compliance/page/product/grc-policy-a...

*************************************************************************************************************
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.

Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]

****************************************************************************************************************

Obed3
Tera Contributor

Hi Arun,

 

The Issue Triage process (OOTB) will only flow to be a risk event in certain conditions. For example, if the Issue type is an Incident or Loss Event (Attachment 1), the Result field at the bottom will have a new choice to Confirm as a Risk Event (Attachment 2). Note that Risk Events created through this flow will automatically have the associated Issue Triage record populated in the 'Issue Triage' related list of the created Risk Event (Attachment 3).

 

It is crucial to understand that in Risk Management, Issues and Risk Events are treated differently, hence why there are distinct pathways depending on the 'Issue type'. An issue is typically a deficiency or gap in control, whereas a risk event (or risk incident/exception) is the occurrence of a risk - which can include an actual impact or near-misses. This explains why some of the choices under Issue type will only have results consistent with creating Issues, while only an incident or loss event will allow you to flow into a Risk Event record.

 