How to write client script for planned end date can't be more than 2 month from planned start date

PRAGHATIESH S
Tera Expert

Hi,

 

I have created one check box (u_type) on the change form (change_request table).

(1) If check box is false...planned end date can' be set more than 2 months from planned start date.

(2) If check box is true....Planned end date can't be set more than 6 months from planned start date. if we set less than 6-month, error message should get show.

Can anyone help me on the client script?

1 ACCEPTED SOLUTION

Pratik Malviya
Tera Guru

Hi @PRAGHATIESH S ,

 

You can achieve this by UI policy easily, You need to write 2 UI policy for both these condition.

 see 1 of the I have created other you can replicate.

PratikMalviya_0-1674809141972.png

 

PratikMalviya_1-1674809198725.png

Please mark correct if it works for you.

 



 

Please mark the appropriate response as correct answer and helpful, This may help other community users to follow correct solution.
Thanks,
Pratik Malviya

View solution in original post

5 REPLIES 5

Pratik Malviya
Tera Guru

Hi @PRAGHATIESH S ,

 

You can achieve this by UI policy easily, You need to write 2 UI policy for both these condition.

 see 1 of the I have created other you can replicate.

PratikMalviya_0-1674809141972.png

 

PratikMalviya_1-1674809198725.png

Please mark correct if it works for you.

 



 

Please mark the appropriate response as correct answer and helpful, This may help other community users to follow correct solution.
Thanks,
Pratik Malviya