The primary route for an emergency change progresses is in which order
New Authorize Scheduled> implement>review>closed
New->Scheduled-Implement >review>Coved
New-Assess->Authorize-Scheduled>Implement >Review >Closed

2 REPLIES 2

Valmik Patil1
Kilo Sage

Hello @Sirithalluri ,

 

Emergency change processes in following order ,

 

New-Assess->Authorize-Scheduled>Implement >Review >Closed

 Screenshot 2024-11-11 at 1.43.31 PM.png

Thanks,

Valmik Patil

Valmik Patil1
Kilo Sage

Hello @Sirithalluri ,

 

If you found answer given by me helpful then ,

Please accept solution from your end.

Thanks,