Project Planned End Date Calculation?

Edwin Fuller
Tera Guru

I understand the planned end date for a project is calculated using the below formulas. However, I can't find where the calculation is actually being done whether it be a client script or business rule. Can someone show me where to locate how the planned end date for a project is calculated?

Planned End Date = Planned Start Date + Planned Duration

or

Planned End Date = Actual Start Date + Planned Duration

1 ACCEPTED SOLUTION

sachin_namjoshi
Kilo Patron
Kilo Patron

Hi Edwin,



Below client script is used to calculate project planned end date.



Calculate End Date From Duration



Also, please check below business rule which calculate project end date



Recalculate



Regards,


Sachin


View solution in original post

5 REPLIES 5

Edwin mentioned "I've checked the default value, and there's no default value."
I'm having the same issue even with no default value.  Any ideas what else could be causing this? 

Planned Duration[duration] w no default value.PNG