Resource Allocation hours calculation logics in Resource Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-04-2024 01:12 AM - edited 09-04-2024 01:13 AM
How can I know exactly a Resource Allocation's hour is calculated ? I created 6 Resource Plans type "Group" with the same start date and end date. The first 3 resource plans are having hours spread even for the first 3 users but the last 3 resource plans are not correct when one of the users have different schedule and even if users don't have schedules if I created too many Resource Plans the hours inside Resource Allocations will become not even. The logics seem to be checking records inside table "resource_allocation_daily" but I can't understand how the code works for case users have different schedules and also running out capacity in "resource_allocation_daily"
Example not even hours spread among users