Hi All,
I like to see if there is factuality in DPR to add a new phase while release is already in progress.
For example - If I am in SIT phase and I need to Perform SIT again but in place of restarting phase I would like to add a new Phase call SIT Take 2.
I am aware that there is a option to restart that existing phase but I am looking if we can add custom phase?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-14-2026 08:30 AM
You need to make the change in the template so that you can add a phase like this. @PKJS
Regards
Dr Atul G. - Learn N Grow Together ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
******************************************************************************************
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-16-2026 03:56 PM
Thanks for your reply Atul,
I like to understand if we can add new phase in already running release (existing)?
Updating template will be helpful in creating new release.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-16-2026 08:32 PM
Hi @PKJS ,
Hi,
DPR doesn’t support this right now.
Everything is driven from the template only, so please create or modify the template and reuse it for release creation.