Do you allow Changes to be submitted where the start and end of the change can be 2-3+ months?
Thanks
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-06-2024 09:51 AM
That's more of a release or a project from our perspective and we don't track those in change.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-06-2024 09:56 AM
So how did you approach the Windows 11 upgrade with 120K devices from a CHG record perspective? What was submitted and tracked within the CHG?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-06-2024 12:13 PM
It was one large change flagged as high risk spanning 15 months. High risk is our highest level of change requiring sign off from executive and extensive plans, It included three phases, internal IT testing, targeted testing, and then general deployment. It still on going.