Hi ,in problem Management ,need to create RCA and Preventive Action task automatically
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-08-2023 01:27 AM
Hi All,
I have a requirement to create Problem records that will have 2 tasks created automatically - a) the RCA task and b) the Preventive Action task.
how to achieve this
Please help with this it is urgent
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-08-2023 02:09 AM
Hi @MK21 ,
You can create a flow through flow designer for creation of the two tasks for problem records that will be created.
If my answer has helped with your question, please mark my answer as accepted solution and give a thumb up.
Best regards
Anders
If my answer has helped with your question, please mark my answer as the accepted solution and give a thumbs up.
Best regards
Anders
Rising star 2024
MVP 2025
linkedIn: https://www.linkedin.com/in/andersskovbjerg/