How do a schedule a monthly task?
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-22-2022 09:48 PM
I have two request to create two monthly tasks:
1. Create a monthly task on the 1st of every month and assign to a specific assignment group
2. Create another monthly task on the 3rd of every month and assign to a different assignment group.
How do I go about doing that?
Labels:
- Labels:
-
Service Operations Workspace
2 REPLIES 2
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-22-2022 10:06 PM
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎06-22-2022 10:15 PM
Another way is to create tempates for tasks and then use
System Definition -> Scheduled Jobs -> New -> Automatically generate something (a change, an incident, a ci, etc) from a template
to generate tasks every month