04-27-2020 08:11 AM
hi i am working in itsm stimulator, pls give solution for below task .
Add a new risk condition: "Insufficient lead time - Normal Change" so that if lead time of 7 days is not met for Normal change requests, Risk should be set as High (NOT VERY HIGH), Impact should be left alone for changes where Type is Normal Change
Solved! Go to Solution.
- Labels:
-
Change Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-21-2020 03:41 AM

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
05-21-2020 03:41 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-22-2021 01:48 AM
Hi,
Can you advise on how to get the '!=' condition and 'on or before' after the planned start date is relative? I am unable to replicate these conditions for this task on the simulator.
Thanks.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-22-2021 04:16 AM
I resolved this.
Below is the reason:
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
09-15-2023 01:18 AM
In condition,
Planned start date relative "on or before" 7 days from now.
only " before" or "after" options are showing in my instance.
i tried in new instance and restarted instance but that "on or before" option not showing.
Can i consider codition like this:
Planned start date relative before 8 days from now. is this work ??
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 weeks ago
In my condition builder planned start date relative "on or before " option is not showing,what could be the reason for it??