hi i am working in itsm stimulator, pls give solution for below task .

Add a new risk condition: "Insufficient lead time - Normal Change" so that if lead time of 7 days is not met for Normal change requestsRisk should be set as High (NOT VERY HIGH)Impact should be left alone for changes where Type is Normal Change

1 ACCEPTED SOLUTION

Pranay Mahajan
Tera Contributor

Configure below Risk conditions.

Mark helpful if this satisfies..!!

find_real_file.png

 

 

View solution in original post

28 REPLIES 28

Pranay Mahajan
Tera Contributor

Configure below Risk conditions.

Mark helpful if this satisfies..!!

find_real_file.png

 

 

Hi, 

 

Can you advise on how to get the '!=' condition and 'on or before' after the planned start date is relative? I am unable to replicate these conditions for this task on the simulator. 

 

Thanks. 

Sam94
Tera Contributor

I resolved this. 

 

Below is the reason: 

 

When you create a risk condition from scratch you cannot use "!=" and the "on or before" in your conditions. Only way to have them is to find an OOTB risk condition that already uses them...do your modifications on this existing risk condition and then Insert and Stay. Insert and Stay creates a new record and leaves the OOTB one alone.

In condition,

Planned start date relative "on or before"   7 days from now.

only " before"  or "after" options are showing in my instance.  

i tried in new instance and restarted instance but that "on or before" option not showing.

Can i consider codition like this:

Planned start date relative before 8 days from now.  is this work ??

 