What is recommended to do if you incorrectly classify an emergency change as a normal change during the creation and scope stage of the change?
- Cancel and recreate the change as an Emergency change
- Tick the CAB approval required checkbox
- Create an emergency change and link them as parent-child
- Select Revert to New and update the type to Emergency
Labels:
- Labels:
-
Change Management
1 REPLY 1
Options
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
4 hours ago
Hi @sn-ushi
You need to cancel the change you created wrongly and recreate the change as Emergency change.
Answer:
- Cancel and recreate the change as an Emergency change
Thanks and Regards