01-28-2025 12:20 PM
Hi,
In our I made some changes to a catalog item DEV environment including updating the flow. However, I forgot to activate the flow before I completed the update set and moved it to test. How can I get the flow to my test environment?
Can I create another update set, activate the flow and then complete and move the update set to test?
Pending an answer, I have not yet activated the flow in Dev.
Thank you.
Solved! Go to Solution.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2025 12:23 PM
Hi @Mike LHCG1
Yes, create another update set, activate the flow and then complete and move the update set to test and deploy it after the previous update set.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2025 12:23 PM
Hi @Mike LHCG1
Yes, create another update set, activate the flow and then complete and move the update set to test and deploy it after the previous update set.