Is there a way for change tasks to be generated in a particular order??

Ear19
Giga Expert

I have a requirement for the change tasks on a normal change to be generated in a order.  I don't see anywhere that you can place an order on the tasks from the Change Task Workflow.  I attempted to create an execution plan.  See attached but tasks still generated out of order.  Is there anything else I can try to get them in order that my boss is requesting?  

1 ACCEPTED SOLUTION

Community Alums
Not applicable

Hi,

 

1. The ideal solution for this requirement would be to create Change Task 2 after the completion of Change Task 1, and Change Task 3 after the completion of Change Task 2 and so on. So this would follow a sequential flow.

 

You can make use of the "Wait for Completion" field on the "Create Task" activity in your workflow:

find_real_file.png

 

2. If you want your all of your change tasks to be created in parallel, then you need an identifier to understand what tasks must be worked on first. 

You can set the "Order" field on the change tasks, so Your Change task 1 will have an 'Order' of 100, your Change task 2 will have an 'Order' of 200 and so on.

 

find_real_file.png

 

 

So under the "Change Tasks" related list on change form, set the sort by on 'Order' column:

find_real_file.png

 

 

 

Set the sort as default in the Related list entry:

 

find_real_file.png

View solution in original post

5 REPLIES 5

From where is this- Order results by the following fields is coming? The one highlighted?