Report - Change Request and Change Task

riagarwal
Tera Expert

Need to create a report, where I can see the Main Line as Change Request and then the Sub lines as the Change Task related to that CHG with some details. 

for example: 

  1. CHG1134 |  [Details]
    1. CTASK 1 [Details]
    2. CTASK 2
    3. CTASK 3
  2. CHG2365
    1. CTASK 1
    2. CTASK 2
    3. CTASK 3
1 ACCEPTED SOLUTION

AnubhavRitolia
Mega Sage
Mega Sage

Hi @riagarwal 

 

You can create 'List' type Report for Change Task table and can make 'Change Request' field as Group by.

 

I will look like as below screenshot:

AnubhavRitolia_0-1690552247333.png

 

 

 

Please mark this as correct answer and helpful if it resolved, or mark this helpful if this help you to reach towards solution.

Thanks
Anubhav Ritolia
ServiceNow Rising Star 2023

View solution in original post

1 REPLY 1

AnubhavRitolia
Mega Sage
Mega Sage

Hi @riagarwal 

 

You can create 'List' type Report for Change Task table and can make 'Change Request' field as Group by.

 

I will look like as below screenshot:

AnubhavRitolia_0-1690552247333.png

 

 

 

Please mark this as correct answer and helpful if it resolved, or mark this helpful if this help you to reach towards solution.

Thanks
Anubhav Ritolia
ServiceNow Rising Star 2023