Report creation whose pending state is more than 10 days
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-17-2022 10:51 AM
Hi,
Is it possible to achieve the incident report creation where incident state is in pending for more than 10 days
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-17-2022 10:58 AM
Hello Priyanka,
There is an out of the box metric definition for Incident State Duration. You could report on the metric_instance table with a condition of Start Relative Before 10 days ago and value is {your pending state} against this definition.
Please mark my answer as correct/helpful if it has helped you.
Thanks,
Logan
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎02-25-2022 05:32 PM
Hello Priyanka,
Is there anything else I can assist you with? If not, would you mind marking my reply as correct so that it shows as solved for others who may have the same question in the future.
Thanks,
Logan
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-13-2022 08:53 AM
Is there a way, when calculating the number of day in pending state, to exclude weekend days and possibly also holiday?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎07-16-2022 06:16 PM
Hello Dom,
You would need to utilize a schedule to achieve this. The OOB definition does not follow a schedule, instead is standard duration based (i.e. 24x7x365) so you would need to create one yourself.