I need two level of Approval in Emergency Change.

The requirement is:

1. When state change from New to Authorise. The first level of Approval should go to Change Management Group.

Once change manager approves that, then the second level of Approval should go to eCAB Groups.

 

Currently, what I did is, I have create a Change Approval Policies for eCAB, and Change Management Group Approval.

But when state change to Authorise, Approval is going to both the groups simultaneously.

 

Do we need to Modify workflow or Flow Designer. Can anyone help with me in this.

1 REPLY 1

Dr Atul G- LNG
Tera Patron
Tera Patron

Hi @anil_mishra11 

 

The reason is both the groups has same conditions, in this case try to change the order and test.

 

https://www.servicenow.com/community/itsm-forum/how-to-trigger-sequence-approvals-in-change-request/...

 

https://www.servicenow.com/community/developer-forum/dynamic-number-of-approvals/m-p/1788491

 

https://www.servicenow.com/community/now-platform-forum/flow-designer-sequential-approvals/m-p/10788...

 

*************************************************************************************************************
If my response proves useful, please indicate its helpfulness by selecting " Accept as Solution" and " Helpful." This action benefits both the community and me.

Regards
Dr. Atul G. - Learn N Grow Together
ServiceNow Techno - Functional Trainer
LinkedIn: https://www.linkedin.com/in/dratulgrover
YouTube: https://www.youtube.com/@LearnNGrowTogetherwithAtulG
Topmate: https://topmate.io/atul_grover_lng [ Connect for 1-1 Session]

****************************************************************************************************************