Hi,

I know this must get asked all the time but I'm not finding it in any postings.  Is it possible to include the run date and time in either the title of a report or as a column in the report?

Thanks for any information.

:{)

 

1 ACCEPTED SOLUTION

johnfeist
Mega Sage

After several good suggestions and a lot of research I've come to the conclusion that the way reporting is currently built/configured, what I want to accomplish cannot be done.

I'm going to put in an enhancement request that header/footer templates be selectable when configuring the report.

View solution in original post

6 REPLIES 6

Thank you Prateek.  The two articles you cite are for including the run date/time in the subject of the email for a scheduled report.  I'm looking to either include the date/time stamp in the actual report.

 

:{)

The question said add Date and Time to the Report Title.  How do your suggestions address this?

Ron Hoyt.

Tracy Davis
Giga Guru

Try looking at 'Header Footer Template' under Report module.

You can set the headers or footers to include run dates, Report Name, etc.