The CreatorCon Call for Content is officially open! Get started here.

Report on CR dates difference

SS6
Tera Expert

Hi All ,

I want to configure a report on difference between the planned start and end date versus actual start and end date , potentially this report should give me a list of CR's which has the Actual start date - end date (days count in between these date) is greater than / higher than the actual start date - end date (days count in between these dates).

In a way that I will have a list of CR's for which the planning dates has gone wrong .

Please advise how to achieve this requirement.

3 REPLIES 3

Arnoud Kooi
ServiceNow Employee
ServiceNow Employee

Is this what your looking for?



find_real_file.png


May be not exactly but definitely partially yes.



Thanks for your reply, I introduced Check box in to the table and achieved this requirement .


eamoncampbell
Tera Contributor

any ideas how to report on [Actual start] is more than 30 mins after [Planned start]?