Hi All ,
I want to configure a report on difference between the planned start and end date versus actual start and end date , potentially this report should give me a list of CR's which has the Actual start date - end date (days count in between these date) is greater than / higher than the actual start date - end date (days count in between these dates).
In a way that I will have a list of CR's for which the planning dates has gone wrong .
Please advise how to achieve this requirement.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-08-2017 05:12 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎11-08-2017 08:41 PM
May be not exactly but definitely partially yes.
Thanks for your reply, I introduced Check box in to the table and achieved this requirement .
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
‎09-25-2019 06:24 AM
any ideas how to report on [Actual start] is more than 30 mins after [Planned start]?