I cannot edit the component on a copy of the Agile 2.0 Sprint dashboard. I am trying to edit the components Sprint Burndown and Sprint Burnup. When I click on Edit Component on the Configuration menu, I get the message "Component not found." Is there a way to edit this component? Currently, there is no data in the report.
I am running the Data Collector job "[Scrum] Daily Data Collection." Is there a different job I need to be running? I also need to filter the component so that it only shows sprints that are in a certain program.
Eventually, we will be moving to EAP and Collaborative Work Management. In the meantime, I need to create a report that shows the percentage of each state of all stories in each sprint. I created an indicator that captures the state, but I cannot figure out a way to group it by the sprint.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
Hi @clmaherosu
1. If you are working in a custom application scope, you may not be able to edit ServiceNow out-of-the-box (OOTB) dashboard components . Validate it
2. The ability to edit widgets is generally restricted to the creator/owner of the dashboard or an admin.
- Navigate to Performance Analytics > Dashboard Administration.
- Open your copied dashboard record.
- Change the owner to yourself or an administrator
3. Ensure the scheduled job "[Scrum] Daily Data Collection" is active.
4. Verify the sprints have a Planned end date
5. If you recently cloned your instance, try in Incognito/Inprivate browser
6. Instead editing the broken widgets , you can try to add the existing Sprint Burndown and Sprint Burnup reports again
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
yesterday
Thanks for responding! I am the owner and an admin, the job is active (but I don't know for sure that this is the job that is needed to populate this report because I can't edit the component); the sprints all have a planned end date, and I do not see a way to re-add a component.
I was wondering if reports were built using UI Builder, but I have been unable to find the component there either.