Get a first look at what's coming. The Developer Passport Australia Release Preview kicks off March 12. Dive in! 

In which script the estimated delivery date is calculated to display for product

robinbkumar
Tera Contributor

Hi, 

I am new to UI builder and S2P module. I am unable to find from which script the estimated date of delivery is counted and displayed for any product. Actually, I have requirement to now allow lesser date than estimated delivery dates of a product for specified date radio button. Please help

 

 

2 REPLIES 2

Ankur Bawiskar
Tera Patron

@robinbkumar 

which record is that?

Regards,
Ankur
Certified Technical Architect  ||  10x ServiceNow MVP  ||  ServiceNow Community Leader

The estimated date is calculated from the 'sn_shop_supplier_product' table's 'Total lead time in days' field from today's date. 

 

Example: The product shown in screenshot is Grohe... which has 'Total lead time in days' as 41. Hence from today + 41 days is 16th Feb 2025. It is calculated like this. But, I am unable to find from which script in Ui builder these calculations are happening.