Scripted Metrics do not run unless there is another duration metric for the same field

Jan60
Tera Contributor

Hello,

 

in my PDI I created a script based Metric Definition to calculate a value instead of a duration.

This metric definition was not executed and did not create metric instances upon changes to the field in the change request record.

 

It started to work only after I created another metric of type "Field value duration", which had the same or a lower order number. As soon as I delete this additional "Field value duration" metric or put the order number above the one of my scripted metric definition, it stops working.

 

Jan60_0-1724913027602.png

 

Does anybody have an idea, how to make the script based Metric Def work without the second one?

 

 

 