Hi ,
We have an issue with the way the SPM works - projects are being G3 approved , it was realized that approving G3 was not changing the state of the project to Completed.
The expected behavior of the tool is that once G3 is approved, the project is fully COMPLETED and State must be automatically changed to "Closed Complete" without any additional input from the users (users shouldn't have to change any tasks). Once G3 is approved.
I have attached screenshot for the reference.
Can anyone help me on this how we can do ?
TIA
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
Wednesday
Hi @sudheermandala2 ,
the system does not automatically mark a project as Closed Complete when G3 is approved. OOB ServiceNow determines a project's Closed Complete state based on its tasks, not approval stages like G3....Project State Depends on Tasks, Not Approvals
Check these articles:
https://www.servicenow.com/community/spm-articles/understanding-project-states/ta-p/2303762
If you found my response helpful, please mark it as ‘Accept as Solution’ and ‘Helpful’. This helps other community members find the right answer more easily and supports the community.
Kaushal Kumar Jha - ServiceNow Consultant - Lets connect on Linkedin: https://www.linkedin.com/in/kaushalkrjha/