Approved Start Date and Approved End Date in Project

SK51
Tera Contributor

We are in the midst of upgrading from Madrid to Paris. 

Understand that there are 2 new fields: Approved Start Date and Approved End Date in Project. 

However - just curious - for those existing projects, where will the Paris version pluck the value and insert into these 2 new fields? 

I have done some checking - it doesn't follow those planned start and end date from demand. 

Any idea? 

 

 

 

1 ACCEPTED SOLUTION

Rae Ann Prasnic
ServiceNow Employee
ServiceNow Employee

I am fairly confident, for existing projects created in Madrid...after you upgrade to Paris the new date fields of approved start date and approved end date will remain empty. 

find_real_file.png

Please mark reply as helpful or correct if applicable (I'm working on a badge!). Thanks, Rae Ann

View solution in original post

6 REPLIES 6

Hi Rae Ann, 

 

Thanks. 

I went through and checked on it. 

Those projects which have some incorrect value populated into the Approved end date is due to old script used in Create Project. 

 

For those projects created way much earlier than that, the Approved start and end date do appear as empty. 

 

Thanks a lot.

Hi

You may feel free to close this thread with marking correct and helpful.

Thanks & Enjoy.

BR

Dirk