Hello,
It seems there is no option to allocate budget to sub-projects.
I would like to confirm with the SN product team, if my underestanding is correct that the budget can be allocated on the Parent project, but it's portion cannot be allocated to the sub-projects?
Or are there any settings that can change this behaviour?
Additionally, could you please confirm that on the Strategic Planning workspace, only the parent projects should be visible in the portfolio plan and sub projects will never be displayed?
Thank you
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
2 hours ago
Hello @Alpa82 ,
Thanks for connecting with community.
You are correct - OOTB budget can be allocated to the parent project and not to the sub project.
There is no settings to switch on the budget allocation for sub project.
I am not in front of the instance but I believe you can see both project and sub project on the portfolio plan prioritization. (given they adhere to the portfolio plan criteria). You can test this but I am pretty sure both are available.
If the response is useful please mark it correct to help me and the community members.
Happy SPM Journey!
Thank You!
Namita Mishra