Can Resource Plans (in Workbench) autochange dates with the Project (also in Workbench)

JSWATON
Tera Contributor

Is there a way to change resource plan dates in Project & Resource Workbench if we have not migrated to Project & Resource Workspaces?

I want to change project dates and I want all associated resource plans to shift with the new dates. The resource plans are associated to a project, but not to an individual line in the project.

 

We are in Xanadu.

 

~Jack

 

0 REPLIES 0