Join the #BuildWithBuildAgent Challenge! Get recognized, earn exclusive swag, and inspire the ServiceNow Community with what you can build using Build Agent.  Join the Challenge.

Can Resource Plans (in Workbench) autochange dates with the Project (also in Workbench)

JSWATON
Tera Contributor

Is there a way to change resource plan dates in Project & Resource Workbench if we have not migrated to Project & Resource Workspaces?

I want to change project dates and I want all associated resource plans to shift with the new dates. The resource plans are associated to a project, but not to an individual line in the project.

 

We are in Xanadu.

 

~Jack

 

0 REPLIES 0