Some PDIs are currently unavailable, and PDI actions are paused. View the latest updates here. Read More

Can Resource Plans (in Workbench) autochange dates with the Project (also in Workbench)

JSWATON
Tera Contributor

Is there a way to change resource plan dates in Project & Resource Workbench if we have not migrated to Project & Resource Workspaces?

I want to change project dates and I want all associated resource plans to shift with the new dates. The resource plans are associated to a project, but not to an individual line in the project.

 

We are in Xanadu.

 

~Jack

 

0 REPLIES 0