I am a project manager working as a scrum master on a product. I need to build a resource plan for myself to account for the time I spend each month on doing work on this product. I wanted to really build one resource plan for a quarter at a time. How can I do this for the product? I know you can do resource plans at the task level or at a Sprint or Epic level, but I just want to say I'll be doing X hours each quarter functioning as the Scrum Master on this product.
Let me know what you've done in this scenario.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-02-2024 07:51 PM
Hi,
Before doing any resource plan you need to create your schedule in calendar to add your Holidays, leaves, time off so on this schedule basis resource plan will be calculated capacity of your work.
In resource plan you will have to select start date and end date of your duration. select resource plan planned hours type, put your planned hours so based start and end date Planned hours will be divided and cost will be automatically calculated based on Group, user cost defined in your cost.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-03-2024 03:16 AM
For our company we have made a project per quarter for this exact scenario to block off time and then tracked time to that project for the work performed. We also have done operational plans to block the time off.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-03-2024 05:21 AM
Yeah, I am thinking of using the operational resource plans as they didn't want another project for this work. We are moving several things over to more "product" based work since it never ends. The products are dashboards we build/change and maintain for the organization. It seems they are always asking for changes on the darn things.