How can I Edit/Change Project and Project Task dates. I am not able to adjust the dates. Help?
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2022 06:48 AM
Hi,
I want to change/adjust the Project Task dates. Which I am not able to do as they are read-only. How can I do that?
I have admin access.
Thanks,
Vaishnavi
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2022 07:17 AM
Hello,
Can you share a screenshot as start date will be read only but you should be able to edit end date
Thanks.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2022 07:24 AM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
01-28-2022 07:34 AM
Hello,
The Planned start date and Planned end date of any Project is determined by the dates of the Project task it has within it.
To edit Project task open the task from the related list:-
Then once opened you will be able to edit the planned end date, however the planned start date will be read-only itself:-
Please mark answer correct/helpful based on Impact