How can I Edit/Change Project and Project Task dates. I am not able to adjust the dates. Help?

Vaishnavi35
Tera Guru

Hi,

I want to change/adjust the Project Task dates. Which I am not able to do as they are read-only. How can I do that?

I have admin access. 

Thanks,

Vaishnavi

8 REPLIES 8

Saurav11
Kilo Patron
Kilo Patron

Hello,

Can you share a screenshot as start date will be read only but you should be able to edit end date

Thanks.

Hi,

Approved Start and End date are Editable. Rest are not.

find_real_file.png

Project Tasks(The marked 3) the Planned Start and End dates are not Editable. How can I change the dates?

find_real_file.png

Thanks,

Vaishnavi

 

Hello,

The Planned start date and Planned end date of any Project is determined by the dates of the Project task it has within it.

To edit Project task open the task from the related list:-

find_real_file.png

Then once opened you will be able to edit the planned end date, however the planned start date will be read-only itself:-

find_real_file.png

 

 

Please mark answer correct/helpful based on Impact

 

Hi,

They are not Editable there also,

find_real_file.png

Help?

Thanks,

Vaishnavi