I am unable to associate a single project task with multiple change requests.

Jyoti Ranjan Se
Tera Contributor

Hi everyone,

I'm unable to use a single project task in multiple change requests. Could you please guide me on this issue? I found a product document stating that it's possible, and that linking should create a child project task, but it's not working for me.

Please advise on how to resolve this.
Reference product doc link-https://www.servicenow.com/docs/bundle/yokohama-it-business-management/page/product/project-manageme...

JyotiRanjanSe_0-1749031606374.png

 

1 REPLY 1

Uncle Rob
Kilo Patron

"but it's not working for me"
Can you be more specific?