Importing Actual Time / Cost for projects

Niels Aksel
Tera Guru

Hi guys

We are currently implementing ServiceNow SPM, including Resource Management.

We are planning to integration our corporate time registration system for importing actual hours spent on projects.

 

Is the correct way to generate Time Cards based on time registration data imported? We are not currently using time cards in ServiceNow and do not intend to – I’m just looking for the best way to import actual hours and cost.

 

 Anyone has any experience with this or any pointers for how this is intended to work?

3 REPLIES 3

Ryan S
Kilo Sage

Marked 'helpful' as I have the same inquiry. What was your approach?

Praveen23
Tera Contributor

Same question here. Does anyone have a solution for this.

Marcelo Meringo
Tera Contributor

Hi

As I understand, you are involving two diferente situations
One is for time and the other is for costs.

For times you need to have time cards generates. As we didn't use so we decides to design an automatic process to generate time cards from resurce assignaments. From this process you obtain time in hours for projects and labor costs.
For others costs we developes an interface with SAP using budget position as key.
Hope this could help.

Regards