Having recently attended training, I'm led to believe that if you import a MS Project Plan into SN, it should automatically over-write / delete / update the tasks that are already in SN. Experience tells me that this is not the case in our instance of SN - we end up with duplicate tasks, therefore resulting in multiple tasks; Does anyone else have this experience or knows if this is a functionality that needs to be enabled within SN first?
thanks
Sam

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-02-2023 06:51 AM
If you have existing tasks present then you wont be able to import a project plan. You need to remove all tasks and then only import of a project plan will be possible.
After u import a project plan from mpp and then add few new tasks then it will throw a message that there are few tasks which do not match and hence import cannot be executed. If you delete few tasks then after u import the deleted tasks will be added again when you import.
Hope these helps
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-02-2023 08:14 AM
Hi Dhiren, thank you for your response, that's really helpful
Sam

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-02-2023 11:55 PM
Hi @SamanthaDewitt if my response has helped then please mark the response as helpful/correct so that others can benefit when having similar query.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
02-12-2024 03:29 AM
Hi, can you explain more in details the steps i have to do , i have same problem for a month i can't import MS Project