Issue with Cost Plan Calculation for Resource assignment 'Group'
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-11-2024 05:34 AM
Hi All,
When we are creating a 'Resource assignment' selecting a 'Group' under resource, the cost plan that is getting generated after clicking on 'Generate Labor Cost' is creating cost plan but looks like it is taking the default rate of $50/hours.
We have defined the hourly rate & Average Daily FTE/Hours/Person Days on the group level but still it is not picking that up:
Could anyone please suggest what configuration need to setup so that it cost plan is calculated based on the Group level defined hours? Thank you
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
10-17-2024 05:13 AM - edited 10-17-2024 05:14 AM
Can you check if your Strategic Planning service has been upgraded to the October store release (v4.2.0)? I've found a different issue that this resolved, and I'd recommend giving it a try. (Obviously do this in Dev first - I've found an issue where choice lists in the Scoring Framework are missing some options after the upgrade to 4.2.0, but I'm hoping this isn't a wider issue!)