Issue with Cost Plan Calculation for Resource assignment 'Group'

Trailblazer11
Tera Expert

Hi All,

 

When we are creating a 'Resource assignment' selecting a 'Group' under resource, the cost plan that is getting generated after clicking on 'Generate Labor Cost' is creating cost plan but looks like it is taking the default rate of $50/hours.

Trailblazer11_0-1728649733173.png

Trailblazer11_1-1728649856709.png

 

 

We have defined the hourly rate & Average Daily FTE/Hours/Person Days on the group level but still it is not picking that up:

Trailblazer11_2-1728649938533.png

 

Could anyone please suggest what configuration need to setup so that it cost plan is calculated based on the Group level defined hours? Thank you

 

@Namita Mishra 

5 REPLIES 5

phil_bool_unifi
Tera Guru
Tera Guru

Can you check if your Strategic Planning service has been upgraded to the October store release (v4.2.0)?  I've found a different issue that this resolved, and I'd recommend giving it a try.  (Obviously do this in Dev first - I've found an issue where choice lists in the Scoring Framework are missing some options after the upgrade to 4.2.0, but I'm hoping this isn't a wider issue!)