Migrating from Resource Plans to Resource Assignments - Not appearing

Alex2506
Tera Expert

Hi, 

 

I am trying to migrate plans to assignments. Clicked the 'Migrate resource plans' related link and can see it's successfully created the assignments. However, when I view the project in Project Workspace, I don't see any of them and the sync resources button is greyed out. Any ideas what I'm missing? The system property 'sn_pw.enable_resource_planning' is set to true.

1 ACCEPTED SOLUTION

Alex2506
Tera Expert

Also, if anyone has a similar issue to my original questions, I figured it out. The assignments were set at the project level, not the task level. So, in the project workspace, I had to click 'Display Summary Task' in the settings which now shows them.

View solution in original post

3 REPLIES 3

VinothiniA
Tera Contributor

Hi,

In my case, after clicking Migrate Resource plan , resource plan state is updated to Allocated and getting info message as migration in progress but when I have checked Resource Assignment there is no record tagged . 

Any idea where I have to check this?

 

Thanks

Alex2506
Tera Expert

Hi Vinothini, 

 

Can you try adding the following in the related lists as well and see if they are there? Mine were showing as top task > resource assignment instead of task > resource assignment

Alex2506
Tera Expert

Also, if anyone has a similar issue to my original questions, I figured it out. The assignments were set at the project level, not the task level. So, in the project workspace, I had to click 'Display Summary Task' in the settings which now shows them.