03-27-2017 07:47 AM
When I run my Status Report on a Project it brings in my Risks, Issues and Changes but my Milestones are blank. I have added Milestones as a column to all of my Project Tasks and have set some to True and some to False. Does anyone know what I am missing?
Thanks!
- Labels:
-
Project Portfolio Management
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-27-2017 07:51 AM
Hi Mark,
A screenshot would help here.
Also when you say you are reporting on project (pm_project) table then you wont be able to access fields on pm_project_task.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
12-03-2018 02:19 PM
In order for milestones to show up on your status reports, they have to be marked as "key milestones". Since this post was from a couple of years ago, this might have been resolved, but I thought I'd respond anyways 🙂
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-30-2024 11:04 AM
I am having the same issue. Items are marked in my project workspace as key milestone and the PowerPoint code is the default one.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
06-23-2025 08:05 AM
I am having the same issue that adrianq9 describes above. Is there guidance or are there tips regarding getting milestones (marked as key milestones) to appear on the status report?