03-05-2020 02:13 PM
Hello All,
I am setting up a Rate Model for various Resource Plans.
Rate Model :
Role-> User
Then I have set up the Rate Lines, where for various Users, I have given different Rates.
Once done, I created a Demand and under it, I created a Role-based Resource Plan and I am expecting to see the Planned Cost to be calculated based on the Rate Model that is attached to the Demand. Unfortunately, it is multiplying the Planned hours with $50( not sure where it is coming from) , checked all the related setups.
My requirement is that the Planned cost should be calculated based on the Rate Line associated with the Rate Model applied on the Demand.
Please help me.
Aditi
Solved! Go to Solution.
- Labels:
-
Cost Management
-
Financial Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-05-2020 07:31 PM
It looks like your rate model is not working here. It's not finding any resources and it defaults to the $50 rate.
You need to change the Rate Model attribute entity from "resource plan" to "role" and "resource" and the leave the attribute field to "none". Please note if another resource has those rate lines you cant save it to that rate model. they should look like this
Also, make sure that the "rate line" are well populated and is correctly assigned. The resources plan pull from that list of resources when it does its calculation
I have a rate model with group -> role-> resource and it works just fine. I created your rate model and it would default to the $50 rate.
Here is a video on the rate model to help you understand how it works. I also added an attachment on Rate Model. I hope that helps you out!
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-05-2020 09:05 PM
Thank you Krishna, this is exactly what is happening, the Allocated cost is coming correctly based on the Rate Model, but the Planned cost is taking the
Requested hours * $50.
Can you please guide me how I can attach Resource to the Planned Cost part so that the Planned cost also comes correctly on the Resource plan.
Steps I followed:
As advised I have corrected my Rate Model,
2. Setup the Rate Lines accordingly
Step 3. Created Resource plan using the Rate Model created above, the Allocation hours is coming correctly based on the Rate Model, but Planned hours is incorrect.
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-16-2022 04:04 AM
Hey
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
03-06-2020 03:52 PM
Hi Miguel/Krishna,
Can you please help me fix the Planned Cost on Resource Plan. I have shared all the screen shots for your review.
Thank you
Aditi

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-06-2021 02:40 PM
Doesnt look like anyone had any luck with the use of Rate Models....I have tried several scenarios, Resource Plan, Project,Role, Resource etc. nothing seems to work when you define the resource plan. It just doesnt capture the rates defined in the Rate Lines but defaults to the $50 rate. So frustrating that ServiceNow has not been able to fix this issue
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
04-07-2021 08:57 PM
We saw many customers implemented RateModel without any hiccups.
Is any case not being addressed or basic case itself is not working. Can you please raise a case if anything is not working. Or share further details.