What is the best practice for schedules in RM?
Are people using 8-5 weekdays, just trying to see what the majority ok folks are using
Solved! Go to Solution.
- Labels:
-
Resource Management

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-04-2022 12:42 PM
Hi
By default, all the users are assumed to follow the schedule provided in property “Default Schedule Name(com.snc.resource_management.default_schedule)”. Out Of the box, this property is defaulted to ‘Resource Management Schedule’ which is 8 hours a day, 5 days a week schedule.
To learn more about resource management schedules and capacity calculations, explore this article - link
To learn more about Resource Aggregates, see this article as well - link
If my answer was able to solve your query please mark it as Helpful & Correct.
Thanks,
Abhinay Kumar Nandagiri.

- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report Inappropriate Content
08-04-2022 12:42 PM
Hi
By default, all the users are assumed to follow the schedule provided in property “Default Schedule Name(com.snc.resource_management.default_schedule)”. Out Of the box, this property is defaulted to ‘Resource Management Schedule’ which is 8 hours a day, 5 days a week schedule.
To learn more about resource management schedules and capacity calculations, explore this article - link
To learn more about Resource Aggregates, see this article as well - link